"You could be in within six months."
This is what brokers and landlords tell you. And technically, it's true—if everything goes perfectly, you could be in within six months.
Nothing goes perfectly.
The reality: Geneva office fit-outs average 9-12 months from lease signing to move-in. Understanding why helps you find the buildings that can actually deliver faster.
The Timeline Gap
What They Quote
Month 1-2: Lease negotiation and signing Month 2-3: Design and planning Month 3-4: Permitting Month 4-5: Construction Month 5-6: Move-in
Total: 6 months
What Actually Happens
Month 1-3: Lease negotiation (more complex than expected) Month 3-4: Design and planning (revisions, stakeholder changes) Month 4-6: Permitting (delays, additional requirements) Month 6-10: Construction (surprises, coordination issues, delays) Month 10-11: IT and testing (complications) Month 11-12: Move-in
Total: 12 months
The gap isn't incompetence. It's the accumulation of realistic complications.
Where Time Disappears
Phase 1: Lease Negotiation (+2-4 weeks)
Expected: 4 weeks Reality: 6-8 weeks
What happens:
- Legal review takes longer than planned
- HQ involvement adds approval layers
- Fit-out contribution negotiation extends discussions
- Christmas/summer breaks interrupt process
Phase 2: Design and Planning (+2-4 weeks)
Expected: 4 weeks Reality: 6-8 weeks
What happens:
- Leadership visits and requests changes
- User input generates scope additions
- Furniture selection takes longer than expected
- Multiple design iterations
Phase 3: Permitting (+4-8 weeks)
Expected: 4 weeks Reality: 8-12 weeks
What happens:
- Swiss permitting is thorough, not fast
- Additional fire safety requirements
- Accessibility compliance requests
- Back-and-forth on technical details
This is the biggest variable. Buildings with strong permit authority relationships compress this phase. Those without cannot.
Phase 4: Construction (+4-8 weeks)
Expected: 8 weeks Reality: 12-16 weeks
What happens:
- Contractor availability delays start
- Discovery issues (electrical, HVAC, structural)
- Material lead times longer than quoted
- Coordination between trades
- Permit inspections and remediation
Phase 5: IT and Testing (+2-4 weeks)
Expected: Parallel with construction Reality: 2-4 weeks additional
What happens:
- Construction delays push IT installation late
- ISP installation takes longer than expected
- Testing reveals issues requiring fixes
- AV systems need calibration
Why Some Buildings Deliver Faster
Not all buildings suffer these delays equally. Fast-delivery buildings share characteristics:
Existing Fit-Out Advantage
Impact: Saves 6-10 weeks
Buildings with suitable existing fit-outs from previous tenants eliminate most construction:
- No shell-to-finish construction
- Adaptation instead of creation
- Known infrastructure (power, data, HVAC)
Question to ask: "Is there an existing fit-out? How much of it can we use?"
On-Site Project Management
Impact: Saves 4-6 weeks
When project management sits in the building:
- Decisions happen same-day, not same-week
- Issues are identified earlier
- Coordination is simpler
- No telephone tag between parties
Question to ask: "Who manages fit-out projects? Where do they sit?"
Original Contractor Availability
Impact: Saves 4-8 weeks
When original construction contractors are still available:
- No learning curve on building systems
- Existing relationships with permit authorities
- Spare parts often on-site
- Known coordination patterns
Question to ask: "Are the original construction contractors available for my fit-out?"
Permit Authority Relationships
Impact: Saves 4-6 weeks
Buildings with established permit relationships can:
- Pre-clear common modifications
- Expedite review processes
- Navigate requirements efficiently
- Avoid back-and-forth
Question to ask: "What's your track record on permit timelines? Can I speak to recent tenants?"
Track Record Verification
Impact: Certainty
Buildings that have delivered fast fit-outs recently can do it again.
Question to ask: "Can I contact three tenants who moved in within 12 weeks?"
The 10-Week Building
At LINK Geneva, we've delivered fit-outs averaging 10 weeks. Here's why:
Existing infrastructure: Previous fit-outs provide baseline On-site team: Project management in the building Original contractors: Same teams who built the building Permit relationships: Established over years of projects Track record: Verifiable with current tenants
Not every situation is 10 weeks. Complex requirements take longer. But the structural advantages compress timelines.
The Timeline Negotiation
When committing to a building, protect yourself:
Milestone Commitments
Request lease provisions that establish:
- Key milestone dates
- Consequences for landlord-caused delays
- Mutual obligations and dependencies
Delay Provisions
If landlord-side delays occur:
- Rent abatement during delay period
- Extension of rent-free periods
- Cost coverage for temporary space
Verification Before Signing
Don't sign until you've verified:
- Specific timeline with weekly milestones
- Named project manager with track record
- Contractor availability confirmed
- Permit timeline from similar recent projects
- Reference calls with recent fit-out tenants
The Bottom Line
The 6-month timeline landlords quote isn't a lie—it's a best case that rarely happens.
Smart operators budget for 9-12 months and look for buildings that can genuinely deliver faster. Those buildings exist, but they have specific characteristics: existing fit-outs, on-site management, original contractors, permit relationships, and track records.
Before believing the timeline promise, verify it. Call the references. Ask for the data.
The cost of believing a fantasy timeline: months of delay, budget overruns, and organizational disruption.
The cost of verification: a few phone calls.
LINK Geneva average fit-out timeline: 10 weeks. Our on-site team manages every project with original construction contractors. Request a timeline estimate for your specific requirements.
Ready to see LINK Geneva?
Meet the team who built the building. Verify our claims before you sign.
Related Insights
Landlord Promises vs. Landlord Performance: A Scorecard
Every landlord claims excellent service. Here's how to verify claims before signing and hold landlords accountable after.
72% of Geneva Moves Go Over Budget—Here's How to Avoid It
The majority of Geneva office moves exceed budget. A facilities lead's guide to identifying risks early and avoiding the common traps.
Building Your ExCo-Proof Business Case in 48 Hours
The executive committee meets Friday. Here's how to build a bulletproof Geneva office business case in two days.
The Hidden Landmines in Geneva Office Leases
Swiss commercial leases contain clauses that surprise foreign companies. Here are the landmines to spot before you sign.